Sitetrail

Orchard Row

5 blocks · 54 flats · taken over Jun 2026

Example

As at 17 Nov 2026

Built from the records automatically each month. Follows the order of a lender's monitoring surveyor report (RICS).

Monthly report to the funder · Example

Orchard Row

Period 16 Oct 2026 to 13 Nov 2026 · issued 17 Nov 2026

Example scheme

1Summary and risk register

All five blocks are complete outside. Fit-out is under way in blocks A and B. £5.55m certified of £7.42m in contracts; site evidence supports £5.61m. 9 items need action this month, the largest a claim by Example Electrical Ltd that is £103,500 above the evidence.

FinanceRedMoney paid outside certificates and for another scheme; one drawdown line not paid on.
ProgrammeAmberOutside complete on all blocks. Fit-out behind plan in blocks C to E; idle time recorded.
ContractRedElectrical application above the evidence; pay-less notice deadline running.
Quality and safetyAmberElectrical first fix failed inspection once (block B); re-done and passed.
EvidenceAmberOne reused photo rejected. 18% independent evidence on electrical.

2Finance

Facility
£9,200,000
Drawn to date
£4,766,050
Certified to date
£5,545,700
Cost to complete
£2,654,300
Payments out of the scheme account
Paid against a certificate£4,730,050
Paid on a contract without a certificate£19,850
Paid for work on another scheme£38,400
Paid to a firm with no contract here£14,600
Drawn for a named purpose, not paid on£36,000
By package
PackageContractsEvidencedCertifiedPaid
Site set-up and preliminaries£600,00085%£510,000£427,500
Groundworks and drainage£925,000100%£925,000£878,750
Frame, walls and floors£1,650,000100%£1,650,000£1,567,500
Roofing£398,000100%£398,000£359,195
Windows and cladding£842,00095%£799,900£639,920
Electrical£690,00055%£310,500£294,975
Plumbing and heating£628,00050%£314,000£238,640
Drylining and plastering£548,00055%£301,400£182,210
Kitchens, bathrooms and finishes£765,00010%£76,500£0
External works and landscaping£372,00070%£260,400£161,210

3Programme

Block16 Oct13 Nov
Block AOutside completeOutside complete
Block BWindows · storey 4 of 4Outside complete
Block COutside completeOutside complete
Block DWindows · storey 2 of 2Outside complete
Block EWindows · storey 1 of 3Outside complete

4Construction

Fixed view P02 on 16 Oct 2026. Render of the example scheme.
P02 south-east · 16 Oct 2026
Fixed view P02 on 13 Nov 2026. Render of the example scheme.
P02 south-east · 13 Nov 2026
  • Block B: outside complete
  • Block D: outside complete
  • Block E: outside complete
  • Tower crane taken down
  • Sand stockpile, north-east corner removed
  • Paving laid around the blocks
  • Trees planted along the paths
  • Site cabins and hoarding removed
  • Inside block A storey 2: kitchens and bathrooms fitted in flat 2.1 (360° points C1 to C3).
  • Electrical first fix in block B failed inspection on 21 Oct and passed on 23 Oct.

5Contract and claims

  • RedExample Facades Ltd changed bank details on 10 Nov 2026. Call the firm on the number in the contract (not the one in the email) before releasing the payment.
  • RedExample Electrical Ltd claims 70%, site evidence shows 55%. Certify the evidenced amount only, and send a pay-less notice for the difference with the photos attached.
  • RedPay-less notice for Example Electrical Ltd must go by 23 Nov 2026. Send the drafted pay-less notice with the evidence attached.
  • RedPaid from Orchard Row for work on Example scheme 2. Recover the payment or move it to Example scheme 2 with the fund's written approval.
  • Red£36,000 of drawdown 5 for groundworks and drainage not paid on. Ask for the bank statement line, or return the money to the facility.
  • RedExample Landscapes Ltd paid £19,850 without a certificate. Certify the work these payments cover, or recover them in the next certificate.
  • RedExample Supplies Ltd paid with no contract on Orchard Row. Stop further payments until there is a signed order.
  • RedExample Drylining Ltd: 4 people stood 3 days because of Example Electrical Ltd. Contra-charge Example Electrical Ltd for the standing time.
  • RedPhoto from Lee (Example Facades) matches an older photo. Do not count this entry as evidence. Ask for a new photo taken through the phone link.
  • Amber2 invoices from Example Landscapes Ltd just under the £10,000 approval limit. Get a second approver to check the work, and treat them as one order.
  • AmberExample Plumbing Ltd: 2 people stood 2 days because of Example Facades Ltd. Settle the dispute with the site manager's notes and photos, then contra-charge.
  • AmberExample Electrical Ltd: 3 people stood 1 day because of Example Drylining Ltd. Contra-charge Example Drylining Ltd for the standing time.
  • AmberOnly 18% of the evidence for Example Electrical Ltd comes from anyone else. Ask the site manager for a spot-check: photos of the named rooms within 15 minutes.
Method: monthly visit from the same fixed views; reports from site with the time, GPS and a fingerprint of every photo; AI reads each photo and a person checks anything flagged. Payments are matched to certificates and bank statement lines. This report supports, and does not replace, the monitoring surveyor's sign-off. Example scheme: all figures are invented.