Monthly report to the funder · Example
Orchard Row
Period 16 Oct 2026 to 13 Nov 2026 · issued 17 Nov 2026
1Summary and risk register
All five blocks are complete outside. Fit-out is under way in blocks A and B. £5.55m certified of £7.42m in contracts; site evidence supports £5.61m. 9 items need action this month, the largest a claim by Example Electrical Ltd that is £103,500 above the evidence.
| Finance | Red | Money paid outside certificates and for another scheme; one drawdown line not paid on. |
|---|---|---|
| Programme | Amber | Outside complete on all blocks. Fit-out behind plan in blocks C to E; idle time recorded. |
| Contract | Red | Electrical application above the evidence; pay-less notice deadline running. |
| Quality and safety | Amber | Electrical first fix failed inspection once (block B); re-done and passed. |
| Evidence | Amber | One reused photo rejected. 18% independent evidence on electrical. |
2Finance
- Facility
- £9,200,000
- Drawn to date
- £4,766,050
- Certified to date
- £5,545,700
- Cost to complete
- £2,654,300
| Paid against a certificate | £4,730,050 |
| Paid on a contract without a certificate | £19,850 |
| Paid for work on another scheme | £38,400 |
| Paid to a firm with no contract here | £14,600 |
| Drawn for a named purpose, not paid on | £36,000 |
| Package | Contracts | Evidenced | Certified | Paid |
|---|---|---|---|---|
| Site set-up and preliminaries | £600,000 | 85% | £510,000 | £427,500 |
| Groundworks and drainage | £925,000 | 100% | £925,000 | £878,750 |
| Frame, walls and floors | £1,650,000 | 100% | £1,650,000 | £1,567,500 |
| Roofing | £398,000 | 100% | £398,000 | £359,195 |
| Windows and cladding | £842,000 | 95% | £799,900 | £639,920 |
| Electrical | £690,000 | 55% | £310,500 | £294,975 |
| Plumbing and heating | £628,000 | 50% | £314,000 | £238,640 |
| Drylining and plastering | £548,000 | 55% | £301,400 | £182,210 |
| Kitchens, bathrooms and finishes | £765,000 | 10% | £76,500 | £0 |
| External works and landscaping | £372,000 | 70% | £260,400 | £161,210 |
3Programme
| Block | 16 Oct | 13 Nov |
|---|---|---|
| Block A | Outside complete | Outside complete |
| Block B | Windows · storey 4 of 4 | Outside complete |
| Block C | Outside complete | Outside complete |
| Block D | Windows · storey 2 of 2 | Outside complete |
| Block E | Windows · storey 1 of 3 | Outside complete |
4Construction


- Block B: outside complete
- Block D: outside complete
- Block E: outside complete
- Tower crane taken down
- Sand stockpile, north-east corner removed
- Paving laid around the blocks
- Trees planted along the paths
- Site cabins and hoarding removed
- Inside block A storey 2: kitchens and bathrooms fitted in flat 2.1 (360° points C1 to C3).
- Electrical first fix in block B failed inspection on 21 Oct and passed on 23 Oct.
5Contract and claims
- RedExample Facades Ltd changed bank details on 10 Nov 2026. Call the firm on the number in the contract (not the one in the email) before releasing the payment.
- RedExample Electrical Ltd claims 70%, site evidence shows 55%. Certify the evidenced amount only, and send a pay-less notice for the difference with the photos attached.
- RedPay-less notice for Example Electrical Ltd must go by 23 Nov 2026. Send the drafted pay-less notice with the evidence attached.
- RedPaid from Orchard Row for work on Example scheme 2. Recover the payment or move it to Example scheme 2 with the fund's written approval.
- Red£36,000 of drawdown 5 for groundworks and drainage not paid on. Ask for the bank statement line, or return the money to the facility.
- RedExample Landscapes Ltd paid £19,850 without a certificate. Certify the work these payments cover, or recover them in the next certificate.
- RedExample Supplies Ltd paid with no contract on Orchard Row. Stop further payments until there is a signed order.
- RedExample Drylining Ltd: 4 people stood 3 days because of Example Electrical Ltd. Contra-charge Example Electrical Ltd for the standing time.
- RedPhoto from Lee (Example Facades) matches an older photo. Do not count this entry as evidence. Ask for a new photo taken through the phone link.
- Amber2 invoices from Example Landscapes Ltd just under the £10,000 approval limit. Get a second approver to check the work, and treat them as one order.
- AmberExample Plumbing Ltd: 2 people stood 2 days because of Example Facades Ltd. Settle the dispute with the site manager's notes and photos, then contra-charge.
- AmberExample Electrical Ltd: 3 people stood 1 day because of Example Drylining Ltd. Contra-charge Example Drylining Ltd for the standing time.
- AmberOnly 18% of the evidence for Example Electrical Ltd comes from anyone else. Ask the site manager for a spot-check: photos of the named rooms within 15 minutes.