Block C, storey 1 · Electrical
“3 of us here for second fix but first side of the walls not boarded yet. Can't start.”
AI read the photo: Stud walls with cables run, no boards on either side. Second fix cannot start.
As at 17 Nov 2026
From the phone link, ChatGPT, Claude, WhatsApp imports and the monthly visits. Every report shows where it was made and when, so nobody has to take anyone's word for it. Try it: send one from the contractor phone page and it appears here.

Block C, storey 1 · Electrical
“3 of us here for second fix but first side of the walls not boarded yet. Can't start.”
AI read the photo: Stud walls with cables run, no boards on either side. Second fix cannot start.

Whole site, P02 south-east
“Monthly record: all five blocks complete outside, paving done, planting started.”
AI read the photo: All blocks roofed and clad. Hoarding removed. Paving complete, trees planted along the paths.

Block A, flat 2.1 · Kitchens, bathrooms and finishes
“Kitchen in flat 2.1 fitted, worktop on.”
AI read the photo: Kitchen units and worktop fitted, floor laid, walls painted.
Block D, storeys 1 and 2 · Electrical
“Second fix going well in D, about 60% done across the block.”
AI read the photo: Report without a photo. Place stated only. No evidence of second fix in block D in any photo this month.

Block E, south side · Windows and cladding
“Block E cladding complete, south side.”
AI read the photo: Aerial view of the whole site. Not a close-up of block E.
The photo is a near-exact copy of the drone record from 16 Oct (4 of 64 bits differ), uploaded from the gallery 21 days after it was taken.

Block B, storey 2 · Drylining and plastering
“Boarding and skim done in 2.1 and 2.2.”
AI read the photo: Walls and ceilings boarded and skimmed, screed down, door linings in.

Block B, storey 2 · Electrical
“Electrical first fix re-done and passed. Drylining can start tomorrow.”
AI read the photo: Cables run in the ceiling and studs, ready for boarding.

Block B, storey 2 · Drylining and plastering
“4 of us on site, can't board. Sparks' first fix failed inspection.”
AI read the photo: Stud walls with first-fix cables. Inspection tag on the board. No boarding possible.

Whole site, P02 south-east
“Monthly record: block E windows going in, paving started.”
AI read the photo: Blocks A to D clad. Block E windows up to storey 2. Paving started around the blocks.