Sitetrail

Orchard Row

5 blocks · 54 flats · taken over Jun 2026

Example

As at 17 Nov 2026

Facility

£9.2m

£4.77m drawn so far

Certified

£5.55m

of £7.42m in contracts

Evidenced on site

£5.61m

Work the dated photos and visits support

Money at risk

£335k

9 flags to act on

Paid idle time

£4,800

3 times a crew could not work

Act on these first

Act now

Example Facades Ltd changed bank details on 10 Nov 2026

£119,985

The change came by email and has not been checked by phone. The next payment (£119,985) is held.

Next step:Call the firm on the number in the contract (not the one in the email) before releasing the payment.

Act nowElectrical

Example Electrical Ltd claims 70%, site evidence shows 55%

£103,500

Application 4 (16 Nov 2026) for electrical claims 15 points more than the dated photos and reports support.

Next step:Certify the evidenced amount only, and send a pay-less notice for the difference with the photos attached.

Act nowElectricalDeadline 23 Nov 2026

Pay-less notice for Example Electrical Ltd must go by 23 Nov 2026

£103,500

Application 4 is not yet certified. Final date for payment is 30 Nov 2026. If no pay-less notice is sent by 23 Nov 2026, the full amount claimed becomes due, whatever the evidence shows.

Next step:Send the drafted pay-less notice with the evidence attached.

Latest visit · 13 Nov 2026

View P02 on 13 Nov 2026. Render of the example scheme.
  • All five blocks complete outside. Paving done, planting started.
  • Inside block A storey 2: kitchens and bathrooms going in.
  • Next visit 11 Dec 2026, same fixed views and 360° points.

Claimed, evidenced and certified by package

  • Certified
  • Evidenced on site
  • Claimed beyond the evidence
  1. Site set-up and preliminaries

    85% evidenced

  2. Groundworks and drainage

    100% evidenced

  3. Frame, walls and floors

    100% evidenced

  4. Roofing

    100% evidenced

  5. Windows and cladding

    95% evidenced

  6. Electrical

    55% evidenced

  7. Plumbing and heating

    50% evidenced

  8. Drylining and plastering

    55% evidenced

  9. Kitchens, bathrooms and finishes

    10% evidenced

  10. External works and landscaping

    70% evidenced

Latest from site

Stud walls with cables run, no boards on either side. Second fix cannot start.
Marek (Example Electrical)· 16 Nov, 08:05 · ClaudeBlocked

Block C, storey 1 · Electrical

“3 of us here for second fix but first side of the walls not boarded yet. Can't start.”

AI read the photo: Stud walls with cables run, no boards on either side. Second fix cannot start.

On site by GPSLogged there and then
All blocks roofed and clad. Hoarding removed. Paving complete, trees planted along the paths.
Drone visit 6· 13 Nov, 10:20 · Drone visit

Whole site, P02 south-east

“Monthly record: all five blocks complete outside, paving done, planting started.”

AI read the photo: All blocks roofed and clad. Hoarding removed. Paving complete, trees planted along the paths.

On site by GPSLogged there and then
Kitchen units and worktop fitted, floor laid, walls painted.
Sofia (Example Interiors)· 12 Nov, 14:02 · Phone linkDone

Block A, flat 2.1 · Kitchens, bathrooms and finishes

“Kitchen in flat 2.1 fitted, worktop on.”

AI read the photo: Kitchen units and worktop fitted, floor laid, walls painted.

On site by GPSLogged there and then