Where the money went
Every payment is tied to a contract, a certificate and the site evidence behind it. Anything that is not, is flagged.
Drawn from the facility
£4.77m
of £9.2m
Paid against certificates
£4.73m
30 payments
Paid or drawn outside the rules
£108,850
See the lines below
Due, not yet paid
£538k
£119,985 held: bank details changed
Money out of the scheme account
| OKPaid against a certificate | £4,730,050 |
|---|---|
| FlagPaid on a contract without a certificate | £19,850 |
| FlagPaid for work on another scheme | £38,400 |
| FlagPaid to a firm with no contract here | £14,600 |
| FlagDrawn for a named purpose, not paid on | £36,000 |
Built from the bank statement lines and invoices uploaded each month. AI reads each document; a person confirms it before it counts.
By package
- Certified
- Evidenced on site
- Claimed beyond the evidence
Site set-up and preliminaries
85% evidenced
£510k of £600k
Groundworks and drainage
100% evidenced
£925k of £925k
Frame, walls and floors
100% evidenced
£1.65m of £1.65m
Roofing
100% evidenced
£398k of £398k
Windows and cladding
95% evidenced
£800k of £842k
Electrical
55% evidenced
£311k of £690k+£104k claimed
Plumbing and heating
50% evidenced
£314k of £628k
Drylining and plastering
55% evidenced
£301k of £548k+£2,880 claimed
Kitchens, bathrooms and finishes
10% evidenced
£77k of £765k
External works and landscaping
70% evidenced
£260k of £372k
Package summary
| Package | Budget | Contracts | Claimed | Evidenced | Certified | Paid | To complete |
|---|---|---|---|---|---|---|---|
| Site set-up and preliminariesExample Site Services Ltd | £620,000 | £600,000 | £510,000 | £510,000 | £510,000 | £427,500 | £110,000 |
| Groundworks and drainageExample Groundworks Ltd | £940,000 | £925,000 | £925,000 | £925,000 | £925,000 | £878,750 | £15,000 |
| Frame, walls and floorsExample Build Ltd | £1,680,000 | £1,650,000 | £1,650,000 | £1,650,000 | £1,650,000 | £1,567,500 | £30,000 |
| RoofingExample Roofing Ltd | £410,000 | £398,000 | £398,000 | £398,000 | £398,000 | £359,195 | £12,000 |
| Windows and claddingExample Facades Ltd | £860,000 | £842,000 | £799,900 | £799,900 | £799,900 | £639,920 | £60,100 |
| ElectricalExample Electrical Ltd | £720,000 | £690,000 | £483,000 | £379,500 | £310,500 | £294,975 | £409,500 |
| Plumbing and heatingExample Plumbing Ltd | £640,000 | £628,000 | £314,000 | £314,000 | £314,000 | £238,640 | £326,000 |
| Drylining and plasteringExample Drylining Ltd | £560,000 | £548,000 | £304,280 | £301,400 | £301,400 | £182,210 | £258,600 |
| Kitchens, bathrooms and finishesExample Interiors Ltd | £780,000 | £765,000 | £76,500 | £76,500 | £76,500 | – | £703,500 |
| External works and landscapingExample Landscapes Ltd | £390,000 | £372,000 | £260,400 | £260,400 | £260,400 | £161,210 | £129,600 |
| ContingencyNot let | £600,000 | – | – | – | – | – | £600,000 |
| Total | £8,200,000 | £7,418,000 | £5,721,080 | £5,614,700 | £5,545,700 | £4,749,900 | £2,654,300 |
Payments
| Date | Firm | Invoice | Backed by | Amount |
|---|---|---|---|---|
| 30 Nov 2026 | Example Site Services Ltd | PRE-006 | Due 30 Nov 2026 | £57,000 |
| 30 Nov 2026 | Example Roofing Ltd | ROF-004 | Due 30 Nov 2026 | £18,905 |
| 30 Nov 2026 | Example Facades Ltd | WIN-004 | Held | £119,985 |
| 30 Nov 2026 | Example Plumbing Ltd | PLB-004 | Due 30 Nov 2026 | £59,660 |
| 30 Nov 2026 | Example Drylining Ltd | DRY-003 | Due 30 Nov 2026 | £104,120 |
| 30 Nov 2026 | Example Interiors Ltd | KIT-001 | Due 30 Nov 2026 | £72,675 |
| 30 Nov 2026 | Example Landscapes Ltd | EXT-003 | Due 30 Nov 2026 | £106,020 |
| 9 Nov 2026 | Example Landscapes Ltd | EXT-INV-118 | Flagged | £9,950 |
| 9 Nov 2026 | Example Landscapes Ltd | EXT-INV-119 | Flagged | £9,900 |
| 2 Nov 2026 | Example Site Services Ltd | PRE-005 | Certificate | £85,500 |
| 2 Nov 2026 | Example Build Ltd | FRM-005 | Certificate | £235,125 |
| 2 Nov 2026 | Example Roofing Ltd | ROF-003 | Certificate | £132,335 |
| 2 Nov 2026 | Example Facades Ltd | WIN-003 | Certificate | £279,965 |
| 2 Nov 2026 | Example Electrical Ltd | ELE-003 | Certificate | £131,100 |
| 2 Nov 2026 | Example Plumbing Ltd | PLB-003 | Certificate | £119,320 |
| 2 Nov 2026 | Example Drylining Ltd | DRY-002 | Certificate | £104,120 |
Drawdowns
| No. | Date | Amount | To date |
|---|---|---|---|
| 1 | 22 Jun 2026 | £725,563 | £725,563 |
| 2 | 20 Jul 2026 | £697,063 | £1,422,625 |
| 3 | 24 Aug 2026 | £827,403 | £2,250,028 |
| 4 | 21 Sept 2026 | £1,286,538 | £3,536,565 |
| 5 Flag | 26 Oct 2026 | £1,229,485 | £4,766,050 |